Concrete calculator
Enter the length, width and thickness. You see the concrete volume and the approximate materials to mix it.
Materials depend on the mix design. This calculator uses a general-purpose 1:2:3 mix as a reference.
How it's calculated
- Volume = length × width × thickness, with the thickness in metres.
- It adds the margin for uneven ground and spillage.
- Per m³: about 350 kg of cement, 0.55 m³ of sand, 0.8 m³ of gravel and 180 litres of water.
An example
A 4 × 3 m slab, 10 cm thick, needs 1.2 m³ of concrete.
With the reference mix, that is about 420 kg of cement, 0.66 m³ of sand and 0.96 m³ of gravel.
Frequently asked questions
How many cubic feet are in a cubic yard?
27. A cubic yard is 3 ft × 3 ft × 3 ft. Ready-mix concrete is usually sold by the cubic yard.
How much cement is in a cubic metre of concrete?
With a 1:2:3 mix, about 350 kg. Stronger concrete uses more cement.
Should I order ready-mix?
For large pours it is usually more consistent and faster. For small jobs, mixing on site with these amounts is common.
Key terms
- Mix design
- The ratio of cement, sand, gravel and water in a mix.
- Cubic yard (yd³)
- The volume of a cube 1 yard on each side: 27 cubic feet.